Description: |
This contract includes design, engineering, production, assembling &
integration, shipment, commissioning, training, spare parts supply, test
operations and delivery of 27 train sets (135 metro cars).
Contract duration: The total contract duration: 33 months Duration of design,
carbody prototype manufacturing and test: 14 months from the beginning of the
project Production and delivery of the first 11 sets: 24months from the
beginning of the project. Production and delivery of the remaining 15 sets: 33
months from the beginning of the project. |
Project specifications: |
Number of cars per set: 5
Supply type: Overhead catenary
Train configuration: MC-T-M-T-MC
Maximum speed: 80km/h
Supply voltage: 1500VDC
Train total length over couplers: 99382mm
MC car length over couplers: 20501mm
M or T car length over couplers: 19460mm
Car width: 2650mm |
|
 |
|